APA CEO and Managing Director Adam Watson said the business’ decision two years ago to invest in a 25 per cent expansion of the East Coast Grid is already delivering essential capacity to customers and southern markets, particularly in the peak winter periods.
“Two years ago, we could see there was going to be a need for greater gas transmission capacity for the northern producers delivering gas to the southern markets. We wanted to get ahead of this demand to ensure we could support the needs of our customers and our communities” Mr Watson said.
“The first stage of our East Coast Grid expansion is now complete, with the second stage under construction and expected to be complete in readiness for the growing winter demand in 2024.